2.2. Annual Boiler Inspection

Overview

High-pressure boilers must be inspected by a qualified inspector. The inspection includes both an internal inspection and an external inspection of the Boiler.  

 

2.2.1. Scheduling

The annual inspection is monitored by the Department of Building (DOB). The inspection should be scheduled no later than 3 months before the end of the year with a Licensed Master Plumber (LMP). 

2.2.2. Inspection

The internal and external boiler inspection can be done at the same time, if scheduled separately, it should be performed with an approximate gap of six months.

2.2.3. Filing

The inspection report must be filed within 45 days of inspection. If the inspection failed, you have 180 days to correct all deficiencies reported. 

Our experts are ready to answer any questions you may have about the compliance process.

Whether you need to know more about testing requirements or what happens if you miss a critical deadline, we will help you find the information you're looking for. We developed SmartCompliance to automate the entire compliance process, and we know that the NYC regulatory landscape is tricky, so let us help you today.

Speak to an Expert

Discuss this Criteria

Have a question? Want to share your facility's insight? Leave a comment below!

1. Backflow Preventer
2. Boiler
3. Building
5. Elevator
6. Escalator
7. Facade
  • 7.1. FISP
    • 7.1.1. Scheduling
    • 7.1.2. Inspection
    • 7.1.3. Filing
8. Fire Alarm
9. Fire Extinguisher
10. Fuel Tank
11. Generator
12. Gravity Tank
13. Pool
14. Smoke Detector
15. Sprinkler System
16. Standpipe System
17. Hood Suppression